The window for a Vendor to submit a proposal is dictated by the priority of the Purchase Order. This metric measures the vendors ability to submit their proposals in the app within the expected window based on the priority.
When no proposal is needed, then the Purchase Order is not included when scoring the metric.
Purpose / Metric Definition:
Evaluates whether a vendor submitted a proposal within the expected timeframe after entering the "Vendor Proposal Required" status. This metric reflects vendor responsiveness and adherence to service-level expectations based on priority.
Category:
Performance
Logic / Formula:
CASE
WHEN HoursPendingProposal IS NULL THEN NULL
WHEN PO.Priority_Category IN (1, 3) AND HoursPendingProposal <= 24 THEN 1
WHEN PO.Priority_Category = 2 AND HoursPendingProposal <= 48 THEN 1
ELSE 0
END AS Performance_ProposalTurnaround
Scoring Rules:
100% → Proposal submitted within expected time window
Emergency & High Priority: ≤ 24 hours
Standard Priority: ≤ 48 hours
0% → Proposal submitted outside expected time window
Not Scored (NULL) → PO never entered "Vendor Proposal Required" status
Links to Dashboards/Reports that use this metric:
Was this article helpful?
That’s Great!
Thank you for your feedback
Sorry! We couldn't be helpful
Thank you for your feedback
Feedback sent
We appreciate your effort and will try to fix the article